Licences and approvals

Boral Cement clinker grinding facility works approval application


On this page:

EPA’s decision on the works approval application (Updated)*

A works approval has been granted

The works approval (PDF 1.8 MB) issued to Boral Cement Limited (Boral) is for the facility as proposed in the works approval application. The EPA approval process has determined that the proposal meets the requirements of the relevant guidelines, policies and Environment Protection Act 1970.

Prior to the issuing of any operational licence for the facility, Boral is required to demonstrate the effectiveness of the required environmental monitoring, management and controls in protecting the environment and community. These requirements are listed in the works approval conditions and take a particular focus on the potential impacts from noise and dust. Specific requirements in the works approval call for the development of:

  • a final acoustic management plan
  • a final stormwater management plan
  • a final air monitoring and management plan
  • specifications for real-time air monitoring
  • a final dust management plan
  • a reactive management plan for responding to noise and dust.

These plans must include clear supporting evidence, triggers and specific actions which adapt operational practices in response to site conditions. Boral must finalise its designs and submit its plans to EPA before commencing construction.

At the completion of works, and following verification of environmental controls during commissioning, Boral will be required to operate under an EPA licence.

*VCAT appeal

Following EPA’s issue of a works approval to Boral Cement Limited, an application for review of the decision was lodged with the Victorian Civil and Administrative Tribunal (VCAT). VCAT upheld EPA's decision to issue a works approval to Boral.

VCAT ordered that all conditions of the original approval remain unchanged.

Process to date

The works approval was advertised in the Herald Sun, The Age and The Geelong Advertiser on Wednesday 26 July 2017. These applications were open for public comment until 16 August 2017. The application was also referred to the Department of Health and Human Services (DHHS), City of Greater Geelong and Port of Geelong.

Section 22 notice: request for additional information and response

After reviewing the submissions, EPA identified a number of specific environmental issues and subsequently issued a notice to the applicant (under section 22 of the Environment Protection Act 1970) on 24 August 2017, requesting further information. The applicant was required to provide this information by 30 August 2017.

EPA requested information relating to the specific environmental issues including existing background noise levels from existing industries, the cumulative noise impacts at sensitive receptors and proposed increased truck movements.

The following response was received from Boral on 30 August 2017.

Any additional comments on the information provided in response to the issued section 22 notice should be submitted in writing to the EPA.

Submissions

EPA received six submissions from the public. Issues raised in the submissions included, but were not limited to, concerns about increased truck movements in the North Shore area, the high levels of existing industrial background noise and the impact from additional industrial noise.

EPA’s assessment was based on a comprehensive examination of the application in line with the Environment Protection Act 1970 and relevant state environment protection policies (SEPPs) and guidelines. Accordingly, the assessment was limited to examining the environmental impacts of the clinker grinding facility and issues associated with its installation, use and operation.

Background

Boral Cement Limited (the ‘applicant’) applied to the Environment Protection Authority (EPA) for a works approval to construct a new clinker grinding facility at 37-65 Walchs Road, North Shore, Geelong (“Lascelles Wharf”). The applicant proposed to construct equipment and buildings including: enclosed ball mill and covered store; clinker unloading and delivery infrastructure (covered belt conveyors); outdoor product stockpiles and several finished product storage and distribution silos at the premises. The plant will accept and process clinker to produce cement products at a capacity of 1.3 million tonnes per year.

Clinker will be unloaded from ships and delivered to the site via covered belt conveyors from Lascelles Wharf. Following processing, finished product will be transported to the Victorian market via trucks. The facility is proposed to operate 24 hours a day, seven days a week, with approximately two weeks per year shut-down for maintenance and repairs.

Boral requires EPA works approval prior to commencing construction works on the facility and will operate under an EPA licence (subject to approval).

Application timeline to date

  • 20/06/2017 – Final works approval application received by EPA.
  • 26/07/2017 – Public advertising of works approval and public comment period for submissions open.
  • 16/08/2017 – Public comment period for submissions close.
  • 24/08/2017 – Section 22 notice issued requesting further information.
  • 30/08/2017 – Response to section 22 notice received.
  • 20/10/2017 – EPA approved the application with conditions.

How to ask questions

Questions relating to the EPA works approval application should be directed to EPA’s Customer Service Centre on 1300 372 842 (1300 EPA VIC) or by email to contact@epa.vic.gov.au

If you need interpreter assistance or want this page translated, please call 131 450 and ask to speak with Environment Protection Authority Victoria (EPA).

Supporting documents

Page last updated on 9 Aug 2018